TY - JOUR
T1 - Large neighborhood search for an aeronautical assembly line time-constrained scheduling problem with multiple modes and a resource leveling objective
AU - Borreguero Sanchidrián, Tamara
AU - Portoleau, Tom
AU - Artigues, Christian
AU - García Sánchez, Alvaro
AU - Ortega Mier, Miguel
AU - Lopez, Pierre
N1 - Publisher Copyright:
© The Author(s), under exclusive licence to Springer Science+Business Media, LLC, part of Springer Nature 2023.
PY - 2024/7/1
Y1 - 2024/7/1
N2 - This paper deals with a scheduling problem arising at the tactical decision level in aeronautical assembly line. It has the structure of a challenging multi-mode resource-constrained project scheduling problem with incompatibility constraints, a resource leveling objective and also a large number of tasks. We first present a new event-based mixed-integer linear programming formulation and a standard constraint programming formulation of the problem. A large-neighborhood search approach based on the constraint programming model and tailored to the resource leveling objective is proposed. The approaches are tested and compared using industrial instances, yielding significant improvement compared to the heuristic currently used by the company. Moreover, the large-neighborhood search method significantly improves the method proposed in the literature on a related multi-mode resource investment problem when short CPU times are required.
AB - This paper deals with a scheduling problem arising at the tactical decision level in aeronautical assembly line. It has the structure of a challenging multi-mode resource-constrained project scheduling problem with incompatibility constraints, a resource leveling objective and also a large number of tasks. We first present a new event-based mixed-integer linear programming formulation and a standard constraint programming formulation of the problem. A large-neighborhood search approach based on the constraint programming model and tailored to the resource leveling objective is proposed. The approaches are tested and compared using industrial instances, yielding significant improvement compared to the heuristic currently used by the company. Moreover, the large-neighborhood search method significantly improves the method proposed in the literature on a related multi-mode resource investment problem when short CPU times are required.
KW - Aeronautical assembly line scheduling
KW - Constraint programming
KW - Large neighborhood search
KW - Mixed-integer linear programming
KW - Multiple modes
KW - Resource leveling
U2 - 10.1007/s10479-023-05629-3
DO - 10.1007/s10479-023-05629-3
M3 - Article
AN - SCOPUS:85174234577
SN - 0254-5330
VL - 338
SP - 13
EP - 40
JO - Annals of Operations Research
JF - Annals of Operations Research
IS - 1
ER -