A partial flooding of the Blayais nuclear power plant occurred in the Gironde estuary during the storm of 27/12/1999, without compromising the overall safety of the systems. The strength of the phenomena, and the key role of wind-waves, lead EDF to review the extreme hydraulic forcings that act on the plant, in order to enhance the protection of the plant against the flooding risk. Statistic and deterministic (modelling) evaluations of relevant hydraulic hazards (tide, storm surges, wind-waves), in addition to a physical modelling in a wave flume, enabled to design in a rapid and reliable way new protective structures (sea-wall). Studies were completed in october 2000, and main related works have been achieved in the field in march 2001.
| Titre traduit de la contribution | Enhancement of the protective seawall against flooding at Blayais power plant: Combined contribution of numerical and physical hydraulic modellings |
|---|---|
| langue originale | Français |
| Pages (de - à) | 37-44 |
| Nombre de pages | 8 |
| journal | Houille Blanche |
| Numéro de publication | 3 |
| Les DOIs | |
| état | Publié - 1 janv. 2004 |
| Modification externe | Oui |
Empreinte digitale
Examiner les sujets de recherche de « Renforcement de la protection contre l'inondation du front de Gironde sur le site du Blayais: Apports conjoints des modélisations physique et numérique ». Ensemble, ils forment une empreinte digitale unique.Contient cette citation
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver